PMP美國項目管理認(rèn)證的模擬考試的樣題10

字號:

1. There are two major types of reserves used on projects.
    The _____ is for (usually major) scope changes that were
    not considered as part of the original plan, whereas the
    _____ is to compensate for minor changes in estimating,
    escalation factors.
    A. Management reserve, unplanned allowance fund.
    B. Management reserve, contingency.
    C. Contingency fund, management reserve.
    D. Unplanned allowance fund, budgetary reserve.
    E. Unplanned reserve, planned reserve.
    ANS: C
    2. To determine what causes the majority of quality
    problems in a process, a very useful tool is the:
    A. cause and effect diagrams.
    B. flow chart.
    C. control chart.
    D. pareto chart.
    E. trend chart.
    ANS: D
    3. Which of the following is not part of contract
    administration
    A. contract award
    B. performance control
    C. financial control
    D. contract closeout
    E. All of the above are parts of contract
    administration.
    ANS: A
    4. A(n) _____ system is designed to ensure the timely
    availability of nonhuman resources, and includes the
    cost in procurement, shipping/freight, storage and loss.
    A. Inventory control.
    B. Materials management.
    C. Procurement.
    D. All of the above.
    E. A and C only.
    ANS: B
    5. Expectancy theory as applied to project management
    implies that:
    A. The team will work the hardest on those goals that
    are clearly explained by the project manager
    B. The more rewards that the project manager provides,
    the better the performance of the team
    C. Team members will work hardest for those project
    goals that also bring satisfaction to personal goals
    D. Employees will work hardest for those project goals
    which are accompanied by high levels of authority for
    the individual team members
    E. None of the above
    ANS: C
    6. Non-verbal communication includes:
    A. Body movement
    B. Gestures
    C. Facial expressions
    D. The way we move our hands
    E. All of the above
    ANS: E
    7. The formal invitation to submit a price for specified
    goods/services is usually referred to as:
    A. request for proposal
    B. request for quotation
    C. tender invitation
    D. bid invitation
    E. A and B only
    ANS: B
    8. The project scope/charter baseline includes:
    A. Summary of background conditions defining the
    project.
    B. Organization, authority and responsibility
    relationships.
    C. Functions to be performed.
    D. Resource requirement schedule including time
    estimates.
    E. All of the above.
    ANS: E
    9. Which of the following is not an input to quality
    planning?
    A. scope statement.
    B. regulations.
    C. work results.
    D. standards.
    E. quality policy.
    ANS: C
    10. Which of the following networking methods allows
    us to show that the last 10% of one element cannot be
    completed until 62% of a previous element has been
    completed?
    A. PERT
    B. ADM
    C. PDM
    D. All of the above.
    E. A and C only.
    ANS: C